City of Drumright Road Improvement Notice
The City of Drumright will begin several road improvement projects starting Monday, July 13, 2026.
City employees will place a notification card on your door before work begins in your area.
Please plan ahead and park your vehicle in a location where you will be able to access it during construction. Roads will be temporarily closed while paving is in progress, and access to driveways may be limited until the work is complete.
Thank you for your patience and cooperation as we work to improve our city streets.
Roads will be completed in the order listed below:
1 – N Magnolia
2 – Euchee
3a – N California
3b – N California from Drumright St north to Oak St
4 – Fulkerson from Virginia to S California
5 – S California from Broadway to Wood
6 – S Oklahoma from Sixth to end
7 – Third from Duke to S California
8 – Duke
9 – N Maine from Oak to Maple
10 – E Maple from Harley to N Texas
11 – N Harley from Smathers to Stiner
12 – Stiner from Smathers to Ohio
13 – Center from Maple N to end
14 – E Pine from Harley to N Pennsylvania
15 – Oak from Harley to N Pennsylvania
16 – W Pine from Pennsylvania to ByPass
17 – Noble from Haven Hill to Skinner
18 – S Skinner Noble to Second St
19 – Second St from Skinner to Jones
20 – S Bristow from Broadway to Noble